Typical rooftop solar installation timeline in Jaipur:
- Day 0 — Free awareness call with PM Solar (NGO) on WhatsApp / phone
- Day 1-2 — NGO counsellor explains subsidy eligibility, pricing references, and helps you shortlist MNRE-empanelled vendors from the official portal list
- Day 3 — You sign an agreement directly with the chosen MNRE-empanelled vendor; PM Surya Ghar + JVVNL applications are filed
- Day 7-10 — Panels + inverter delivered to site by the empanelled vendor
- Day 10-12 — Vendor performs mounting + panel + inverter installation (2-3 days work)
- Day 35-40 — JVVNL net-meter installed and system commissioned
- Day 65-80 — Subsidy credited to your bank account
Total: 6-8 weeks from first WhatsApp to subsidy in account.