Net Metering Rajasthan — JVVNL / AVVNL / JdVVNL Process & Limits

All three Rajasthan DISCOMs (JVVNL, AVVNL, JdVVNL) allow residential net metering up to 10 kW per connection. PM Solar (NGO) provides free guidance on the application + JE inspection coordination + commissioning report submission. Physical installation by an MNRE-empanelled vendor.

Rajasthan Electricity Regulatory Commission (RERC) Net Metering Regulations 2024 govern all three state DISCOMs:

  • JVVNL (Jaipur Vidyut Vitran Nigam) — Jaipur, Dausa, Sikar, Alwar
  • AVVNL (Ajmer Vidyut Vitran Nigam) — Ajmer, Nagaur, Bhilwara
  • JdVVNL (Jodhpur Vidyut Vitran Nigam) — Jodhpur, Bikaner, Sri Ganganagar, Hanumangarh

Residential cap: 10 kW per connection. Commercial: 500 kW. Settlement period: annual (true-up in March).

Pricing — After PM Surya Ghar Subsidy

2 kW
₹1,34,000
₹60,000 sub
₹74,000
EMI ₹1,536/mo
3 kW
₹1,96,000
₹78,000 sub
₹1,18,000
EMI ₹2,449/mo
5 kW
₹3,20,000
₹78,000 sub
₹2,42,000
EMI ₹5,024/mo

Our expert guides on this topic

MNRE-verified guidance and local Jaipur customer case studies

Frequently Asked Questions

Q.What is the maximum solar system size for net metering in Rajasthan?

10 kW for residential and 500 kW for commercial — per RERC Net Metering Regulations 2024.

All three Rajasthan DISCOMs (JVVNL, AVVNL, JdVVNL) allow net metering up to 10 kW for residential connections and 500 kW for commercial / industrial. Systems above these caps need to use group net metering or virtual net metering arrangements.

Q.How long does JVVNL net-meter installation take in Jaipur?

20-30 days from application — JE inspection happens in 7-14 days; meter installed within 2 weeks after.

Typical JVVNL net-meter timeline in Jaipur: feasibility approval in 7-14 days after the JE site inspection. The bi-directional meter is then installed within 14 days. Commissioning happens immediately after.