The 7 stages of a Jaipur solar installation
1) **Free site survey** — vendor visits, measures roof, checks shadow, JVVNL sanctioned load. (Day 0-1)
2) **PM Surya Ghar application** — https://pmsuryaghar.gov.in filing with Aadhaar + electricity bill. (Day 1-3)
3) **JVVNL feasibility approval** — DISCOM inspects your existing meter, confirms 3-kW capacity. (Day 3-10)
4) **Equipment procurement** — panels, inverter, mounting structure delivered. (Day 8-14)
5) **Physical installation** — 2-day work: 20-panel 3 kW system takes 6-8 field-hours. (Day 15-16)
6) **JVVNL net-metering & commissioning** — bidirectional meter fitted, commissioning report signed. (Day 17-22)
7) **Subsidy disbursed** — ₹78,000 hits your bank account 15-30 days after commissioning; Rajasthan RREC top-up ₹17,000 filed separately. (Day 30-45)